Honey Badger's spot case used US$66 silver. Silver closed the week near US$52
Honey Badger filed its PC Silver technical report with no numbers in the release; the September PEA's spot case now sits about 29% above Friday's price. Barksdale's old PEA used US$4.00 copper and the update is a year away. West High Yield still leans on a 2013 study.
October 30, 2026 at 6:20 p.m. EDT · 2 min read

Three study stories this week, three price decks, and one common problem: the deck was set when metal prices were somewhere else.
Honey Badger: a filing release without the numbers
Honey Badger Silver (TSXV: TUF) announced on October 29 that it filed the NI 43-101 report for the PC Silver Mine PEA, prepared by JDS Energy & Mining with an effective date of June 21, 2026. The release gives no NPV, IRR, capex or price deck. It points back to the September 17 release.
That release used a "Long-Term Consensus (or PEA Case)" silver price of US$50 an ounce: after-tax NPV8% of C$1.165 billion, IRR of 29.3%, C$667 million of pre-commercial production capital and a 22 year life. It also ran a spot case "As at August 31, 2026: Ag US$66.41/oz," and cautioned that "Spot-case economics referenced herein have not been fully run in the live PEA workbook."
Silver was quoted at US$51.58 on October 30 (MetalCharts). By our arithmetic, the August 31 spot case is about 29% above Friday's price. The US$50 base case is now about 3% below spot, so the base case is the one to use.
On resources, the PEA states it "includes Inferred Mineral Resources." The resource is 11.628 Mt measured and indicated and 8.469 Mt inferred. By our arithmetic inferred material is about 42% of resource tonnes. The release does not give the inferred share of the mine plan. The filing release also says the company "holds over 10,000 ounces of physical silver yielding 12% annually," without saying where that yield comes from.
Barksdale: an old copper price and a long wait
Barksdale Resources (TSXV: BRO) is starting an updated PEA at San Javier. The January 2024 PEA "assumed a copper-only heap leach operation at US$4.00/lb copper" and gave a post-tax NPV7% of US$61.6 million, an IRR of 18.1% and initial capital of US$116.8 million. Copper was quoted at US$6.49 a pound on October 30 (MetalCharts). The update will use "consensus long-term prices" and add gold, but it is "expected to be completed in the fourth quarter of 2027." Until then the market has only a 2024 study and a statement that gold "in the range of 250,000 to 400,000 ounces" is not a mineral resource.
West High Yield: a 13 year old study
West High Yield (TSXV: WHY) is raising up to C$1.3 million for "essential operations and general working capital purposes." Its release cites "approximately 10.6 million tonnes of contained magnesium" from a 2013 SRK PEA. A study that old does not reflect current costs or prices.
Company figures are from the linked releases. Metal prices from MetalCharts, quoted separately. Comparisons marked "by our arithmetic" are Listed Ledger's calculations.
More from the Mining Desk
Under the Glass: RUA's Auld Creek study loses US$30.5 million at US$3,700 gold. Bonterra's Barry PEA uses US$3,500
Mining Desk · 10h ago

Starcore's 'second quarter' production report covers one month. Clinch calls its first producing quarter a record
Mining Desk · 10h ago

G Mining is 'on track' with year to date costs above its range. Americas Gold and Silver's record quarter cost US$42.94 an ounce against a US$35 ceiling
Mining Desk · 4d ago